The top question I had prior to budget presentation was “Will the mayor include Community Investment Tax (CIT) funds for the Rays in the 5 year Capital Improvement Program (CIP)?” After some digging, the answer is there’s no line item in the budget that says “Rays Stadium” or even “public facilities”. There is however $26.2 million set aside in Fiscal Year 2027 (FY27) including $23M in the Grants and Aids Budget Reserve fund. All said there is $59.5M in reserve CIT funds in the 3 year forecast with $52.M in the Grants and Aids Budget Reserve Fund. A fund every prior use (FY23-26) was a small placeholder reserve in an operating fund.

Where Tampa's renewed CIT money goes — FY2027 Flow chart. Tampa's FY2027 recommended budget books $38,329,130 of Community Investment Tax revenue. Tampa CIT revenue sends $34,616,667 to New CIT fund (30220). Tampa CIT revenue sends $3,712,463 to Old CIT fund. New CIT fund (30220) sends $24,500,000 to Non-Departmental. New CIT fund (30220) sends $10,116,667 to Fleet CIT Program #7. Non-Departmental sends $23,000,000 to Grants and Aids Budget Reserve. Non-Departmental sends $1,500,000 to Yellow Jacket Improvements (Parks). Fleet CIT Program #7 sends $7,000,000 to Police vehicles. Fleet CIT Program #7 sends $3,116,667 to Fire apparatus. Old CIT fund sends $3,238,823 to Program 6 capital-outlay reserve. Old CIT fund sends $473,640 to Program 6 operating. Grants and Aids Budget Reserve (account 589999) — generic, unexplained in the book. Tampa CIT revenue → New CIT fund (30220): $34,616,667 Tampa CIT revenue → Old CIT fund: $3,712,463 New CIT fund (30220) → Non-Departmental: $24,500,000 New CIT fund (30220) → Fleet CIT Program #7: $10,116,667 Non-Departmental → Grants and Aids Budget Reserve: $23,000,000 Non-Departmental → Yellow Jacket Improvements (Parks): $1,500,000 Fleet CIT Program #7 → Police vehicles: $7,000,000 Fleet CIT Program #7 → Fire apparatus: $3,116,667 Old CIT fund → Program 6 capital-outlay reserve: $3,238,823 Old CIT fund → Program 6 operating: $473,640 Tampa citywide CIT revenue (account 312600, Local Opt-Sales Tax): $38,329,130 Tampa CIT revenue $38.3M Fund 30220, CIT 2026 - 2041 Capital Projects: $34,616,667 New CIT fund (30220) $34.6M CIT 2026 – 2041 Capital Projects CIT Program 6 FY22 - FY26 (1996 tax, winding down): $3,712,463 Old CIT fund $3.7M Program 6, FY22 – FY26 Booked under Non-Departmental: $24,500,000 Non-Departmental $24.5M Fleet CIT Program #7 2026-2041, internal service fund; spent entirely on account 564001 Transp Equip: $10,116,667 Fleet CIT Program #7 $10.1M 100% to 564001 Transp Equip Grants and Aids Budget Reserve (account 589999) — generic, unexplained in the book: $23,000,000 Grants and Aids Budget Reserve $23.0M Unlabeled in the budget book — covers the proposed $20M/yr stadium pledge, with room Capital project 1002862, Yellow Jacket Improvements, Parks and Recreation: $1,500,000 Yellow Jacket Improvements (Parks) $1.5M Law-enforcement vehicle replacement, purchased through Fleet CIT Program #7 (department-tagged Police): $7,000,000 Police vehicles $7.0M Fire apparatus replacement, purchased through Fleet CIT Program #7 (department-tagged Fire): $3,116,667 Fire apparatus $3.1M Old-fund capital-outlay budget reserve: $3,238,823 Program 6 capital-outlay reserve $3.2M Old-fund operating costs: $473,640 Program 6 operating $474K $34.6M $3.7M $24.5M $10.1M $23.0M $1.5M $7.0M $3.1M $3.2M $474K
Tampa receives 21.9% of countywide half-cent collections under the renewed interlocal formula. Amounts are FY2027 recommended. Source: FY2027 budget line items via OpenGov.

There are actually 2 buckets of funds derived from two different half-cent sales taxes. One administered by the state and distributed to cities and counties and the the Hillsborough County collected CIT. The half-cent tax from the state can be used for general spending, the CIT is exclusive to capital improvement projects.

Under Special Revenue Funds Major Revenues for the FY2027 CIT the analysis says “revenues are expected to increase 43.8% when compared with the FY2026 budget due to economic conditions.” Compared to last year’s analysis:

“FY2026 Community Investment Tax revenues are expected to decrease when compared with the FY2025 budget partially attributable to unstable economic conditions and decreased consumer spending.”

Community Sponsor

In 2025 the city collected $34.8M in CIT. In 2026 the city estimated $26.6M. For FY27 they project $38.3M.

However under General Government Major Revenues the analysis for the other half-cent sales tax revenue projections tells a different story.

“9.5% lower than budget and are expected to remain flat for FY2027. This is primarily due to elimination of sales tax on office and commercial space rentals and leases and inflation impacting business and consumer spending.”

Hard to understand how 2 half-cent sales taxes have such divergent analysis. Sure one is collected state wide and distributed to cities and counties and one is specifically Hillsborough County but the “economic conditions” in the county aren’t that different than the rest of the state. Both taxes are sales taxes. It’s illogical to say one is going to grow 43% and the other is performing 10% lower than expected.

What the analysis doesn’t mention is that the renewed CIT cut the school district from 25% to a 5% share so there’s 20% more of CIT funds to distribute. Tampa Monitor estimates that 20% cut is more than $500M over the 15 years the tax was approved for using the city and county’s projected 3% growth. Depending on which analysis you read though, it could be less. The MOU approved by the city and county pledges $417M in CIT funds for the Rays stadium.

Our stories may be republished online or in print under Creative Commons license CC BY-NC-ND 4.0. We ask that you edit only for style or to shorten, provide proper attribution and link to our website.

Support Tampa Monitor

Reader-funded and independent. Every contribution keeps the reporting going.

Choose an amount

Secure payment via Stripe. Other ways to give →

What we're monitoring

The toolshed

Always-on data tools that keep watch between the stories — built and maintained by the Monitor.

The AgendaA reimagined version of council's weekly agenda.Updated weekly
Capital ProjectsThe city's five-year capital plan & life-to-date spending, every project.FY27 snapshot
Agenda KeywordsEmail notification only if keyword appears on the agenda.Public Beta